David Choy Managing Associate
The Court grapples with impact of Covid-19 on European rugby
A recent judgment from the Commercial Courts in European Professional Club Rugby v. RDA Television LLP [2022] EWHC 50 (Comm) centres on the disruption to European rugby competitions as a result of the onset of Covid-19, but the lessons coming out of it apply equally to parties negotiating or seeking to rely on force majeure clauses in any sector.
European Professional Club Rugby (“EPCR”), the governing body and organiser of the European Rugby Champions Cup and the European Rugby Challenge Cup (the “Competitions”), licenced its media rights for the Competitions for four seasons (commencing with the 2018/2019 season) to RDA Television LLP (“RDA”) by way of a media rights agreement (the “MRA”).
EPCR had scheduled the quarter finals, semi-finals and finals of the 2019/2020 Competitions to take place throughout April and May 2020. The date for the end of the season was 20 June 2020.
On 16 March 2020, EPCR announced that the quarter finals were being postponed due to the onset of the pandemic. In mid-May 2020, EPCR set out its intention to schedule all the remaining matches during September and October 2020.
RDA gave notice of termination on 8 June 2020, asserting that it was entitled to do so in accordance with the force majeure mechanism in the MRA.
EPCR did not agree and considered that (by purporting to terminate the MRA) RDA had wrongfully repudiated the MRA. By way of a letter dated 22 July 2020, EPCR accepted this as bringing the MRA to an end.
Under the MRA a force majeure event was defined as “any circumstances beyond the reasonable control of a party affecting the performance by that party of its obligations” and was specifically stated toinclude an “epidemic”.
The force majeure provision, which RDA sought to rely on as grounds for termination, stated:
“26.1. If either party is affected by a Force Majeure Event which prevents that party from performing its obligations under this Agreement, the affected party shall promptly notify the other of the nature and extent of the circumstances in question.
26.2. ….
26.3. If either party is affected by a Force Majeure Event, it shall use all reasonable endeavours to mitigate and/or eliminate the consequences of such Force Majeure Event ….
26.4. If the Force Majeure Event prevents, hinders or delays a party’s performance of its obligations for a continuous period of more than 60 days, the party not affected by the Force Majeure Event may terminate this Agreement by giving 14 days’ written notice to the affected party.” (emphasis added)
The Court found that the pandemic was a “Force Majeure Event” under the MRA by virtue of the reference to “epidemic” and because the pandemic was a circumstance “beyond the reasonable control of a party affecting the performance by that party of its obligations under this Agreement.”
RDA argued that it was entitled to terminate at any time 60 days after 16 March 2020, when it contends that the pandemic first started to “hinder…or delay… [EPCR’s] performance of …” its obligations under the MRA to “stage each Competition each season during the Term”.
EPCR submitted that:
Given it had not been alleged that the operation of the force majeure clause was subject to any implied terms that qualified the ability of either party to take advantage of the force majeure machinery, the Court held that even if the impact of the pandemic was not the true reason for serving the notice of termination (and RDA saw this as a means of inducing EPCR to re-negotiate terms) this did not matter (and would not render reliance on the force majeure machinery invalid, ineffective or a repudiation) if, on a true construction of the agreement, RDA was entitled to serve notice terminating the MRA.
As a matter of construction, the Court held that RDA was entitled to terminate the MRA (which meant that RDA succeeded with its counterclaim). In reaching this conclusion, the Court:
This case turned on the specific wording of the force majeure provisions (as most disputes concerning force majeure do). However, this judgment provides helpful guidance on how the Court may tackle circumstances in which both parties are affected by the same force majeure event (albeit in different ways).
It is also worthwhile noting that, in the absence of it being argued that implied terms should apply to the operation of the force majeure mechanism, the Court placed little weight on RDA’s motivation for terminating the contract. The Court was also critical of EPCR seeking to rely on its own failure to properly notify its counter party of a force majeure event.
Parties should take care when negotiating force majeure provisions, especially in relation to the intended scope of such provisions. Indeed, although the definition of “Force Majeure” in this contract expressly referred to “epidemics”, the definition was widely drafted so as to include “any circumstances beyond the reasonable control of a party affecting the performance by that party of its obligations”, which meant that the impact of Covid-19 would have fallen within the “Force Majeure” definition in any event.
21-09-2022 / Energy & Infrastructure
On 13 September 2022, the UAE Ministry of Justice (MOJ) issued a landmark directive to the President of the Dubai Courts, referring to a recent English Court judgment in Lenkor Energy Trading DMCC v Puri (2020) EWHC 75 (QB) which enforced a UAE Court judgment, and urging the Dubai Courts to take requisite steps to follow the principle of reciprocity when it comes to enforcing English Court judgments in the UAE.
06-07-2022 / Energy & Infrastructure
McGaughey & Anor v Universities Superannuation Scheme Ltd & Anor [2022] EWHC 1233 (Ch) On 24 May 2022, the High Court refused a claim brought against the directors of the Universities Superannuation Scheme (the “USS”), the largest private pension scheme in the UK, for inaction around climate change commitments.
12-05-2022 / Energy & Infrastructure
Refund guarantees are often described as the cornerstones to shipbuilding projects and the buyer’s main security. Although they do not strictly form part of the shipbuilding contract, a shipbuilding project is unlikely to go ahead at all without one. It is therefore important to understand the different types of guarantee instruments, and the impact each has in practice on the guarantor’s obligations to pay and the buyer’s entitlement to recovery. A well-drafted guarantee provides certainty to the parties and strikes a balance between their respective entitlements and obligations.
04-04-2022 / Energy & Infrastructure
Estoppel is a useful tool in litigation, which is usually used to bind one party to a statement or a promise that it has previously expressed causing another to accept or adopt it for the purpose of their legal relations. The Court’s recent ruling in Geoquip Marine Operations AG v (1) Tower Resources Cameroon SA (2) Tower Resources PLC addresses estoppel by convention and recognises the requirement for the common assumption created between the parties to be clear and unequivocal. In this article, we focus on the specifics of the Court decision.
29-03-2022 / Energy & Infrastructure
On 24 March 2022, the Court of Appeal overturned the conviction of a second man, Paul Bond, prosecuted by the Serious Fraud Office (SFO) in relation to alleged wrongdoing by Unaoil.
02-03-2022 / Energy & Infrastructure
R (Finch) v Surrey County Council CA (Civ Div) [2022] EWCA Civ 187 “The task of the court in a claim such as this is only to decide the issues of law. Those issues cannot extend into the realm of political judgment – which is the responsibility of the executive, not the courts …”