
Paul Griffiths Partner
Court construes settlement agreement in contaminated oil dispute
This dispute related to a sale contract for a cargo of crude oil. It was accepted by the parties that the cargo was contaminated. The issue, however, was whether and the extent to which the settlement agreement they subsequently entered into limited the buyer’s right to claim reimbursement for storage fees it incurred to the terminal operator in respect of the contaminated cargo.
The Court was required to construe the terms of the settlement agreement in their commercial context, to consider the scope of the parties’ contractual duty to discuss and agree level of reimbursement in good faith and to determine the prevailing market rate for storage fees based on expert and other available evidence.
On 24 January 2019, the parties entered into a sale contract for a cargo of KBT crude oil for delivery at Omisalj, Croatia. KBT crude oil comes from Iraq and is exported via the Kirkuk-Ceyhan oil pipeline and is loaded into tankers at Ceyhan, Turkey. The cargo was to be delivered at Omisalj either DES (ex-ship) or ITT (transfer from tank at Omisalj under seller’s control).
Pursuant to the sale contract, the seller procured a performance bond of up to US$20 million to secure performance of its obligations under the sale contract.
The cargo was loaded on board the vessel at Ceyhan and arrived at Omisalj in late December 2019. It was discharged into two tanks belonging to the terminal operator, Janaf, at Omisalj and nearby Sisak. When the cargo was tested, it was found to have unacceptably high levels of chloride. This fell foul of Janaf’s terms and conditions because it could adversely affect other cargoes being transported or damage Janaf’s installations.
The parties discussed how to resolve the situation. In the meantime, some of the cargo had already been transported to the buyer’s refinery. The seller had also managed to persuade its supplier to take back some of the contaminated cargo. Janaf submitted a statement of claim for damage caused by the contamination as well as for “ad hocstorage”. This was passed on to the seller.
The vessel that was to lift the cargo going back to the supplier had to do so by no later than 19 March 2020. Therefore, given the time constraints, the parties concluded a settlement agreement on that day.
Clauses 33 to 36 of the settlement agreement were the focus of the parties’ subsequent dispute over storage fees. Clauses 33 to 34 limited the scope for the buyer to pass on any claims from Janaf, subject to the buyer being able to seek an indemnity/reimbursement for claims made by Janaf for storage fees “to the extent that such liability accurately reflects (i) the actual loss suffered by Janaf and (ii) prevailing market rates during the period when the Cargo was stored in the Janaf system.” Further, the parties would discuss in good faith with a view to agreeing the level of reimbursement.
Clause 35 stated that the agreement was in full and final settlement of all claims save, among other things, any claims by Janaf for storage to the extent that the liability reflected actual loss and the prevailing market rates for storage.
Clause 36 stated that any and all claims between the parties would be presented and dealt with in accordance with the 2019 sale contract.
The buyer made a demand for US$2,094,000 under the performance bond. The seller sought repayment of this sum. The dispute was over whether and to what extent the buyer could claim reimbursement in respect of storage charges incurred to Janaf.
The seller contended that the buyer could only recover storage charges that it paid to Janaf if and to the extent that those charges reflected: (i) an actual loss suffered by Janaf; and (ii) prevailing market rates for storage. The buyer contended that the parties were required to discuss in good faith the storage claims but, in the absence of any agreement, the buyer was entitled to claim those costs under the sale contract without the settlement agreement limiting the claim in any way.
The buyer, on the other hand, submitted that, if Janaf's tanks were being used for storage, Janaf suffered an "actual loss". It maintained that the market rates had to be for storage in the circumstances encountered here, namely the emergency and ad hoc storage of this quantity of contaminated crude oil at Omisalj.
The Court cited the decision in Lukoil Asia Pacific Pte Ltd v. Ocean Tankers (Pte) Ltd (Ocean Neptune) [2018] EWHC 163 (Comm) on the correct approach to construing contracts. The Court must ascertain the objective meaning of the language that the parties have chosen in which to express their agreement and consider what a reasonable person in possession of all the relevant and available background knowledge available to the parties at the time of contracting would have understood the parties to have meant.
The Court thought that the basic structure of clauses 33 to 36 was easy to understand. Clause 33 required the buyer to procure that Janaf give up, and prevented the buyer passing on to the seller, any claim arising out of the cargo, save as specifically provided in clause 34.Clause 34 then:
Clause 35 compromised all claims between the parties "arising out of and/or in connection with the delivery of the Cargo", but preserved five specific claims (defined as the "Outstanding Claims"). These included the storage fees.
The Court was not persuaded by the submission that clauses 34 and 35 did not settle anything in respect of Janaf’s storage fees because the parties had agreed that the buyer’s right to make a claim under the sale contract was preserved if the discussion in good faith was unsuccessful. Rather, it thought that these provisions made the seller liable to reimburse the buyer for storage costs up to a fixed limit. The “actual loss” ingredient meant any uplift to the storage fees which was charged to reflect the fact that Janaf was suffering an actual loss due to the contamination of the cargo or due to the emergency nature of the storage. The “prevailing market rates” for storage were to be for storage at Omisalj and Sisak of approximately the volume used for the period in question, on a “spot” basis.
The Court also dismissed the allegation that the seller failed to enter into good faith discussions. The Court did not think that the seller’s conduct was commercially unacceptable and found there was no evidence that the seller had deliberately delayed discussions and been dilatory in its responses in order to allow the performance bond to expire.
As to prevailing market rate, the Court found that the Janaf "default" rate did not reveal the "prevailing market rates for storage". If it was a market rate for storage at all, it was not the type of market rate which was envisaged by the settlement agreement. It was an emergency rate, fixed in the context of the transportation of oil, mostly as a disincentive to delay.
The Court concluded that the rate that the seller had negotiated with Janaf in March 2020 (and which Janaf had offered in December 2019) provided a genuinely negotiated storage rate for Omisalj and treated this rate as good evidence for the market rate for longer term storage for the relevant period. On that basis, the buyer was only entitled to reimbursement in the amount of US$1,062,000 for storage fees and was obliged to return US$1,032,000 from the amount it received under the performance bond.
Storage rates are often kept secret and there is consequently little publicly available information about this market. The Court, therefore, had very few comparables to work with and recognised the limitations of the material with which it was working. It acknowledged that it could not make as precise an assessment of the relevant market rate as might be possible in the context of a different market. Nonetheless, the outcome seems to be a sensible one.
20-02-2023 / Commodities & Trade
In a dispute arising under sale contracts for unleaded gasoline, the Court has held that the buyer’s claims in unjust enrichment for money had and received were time-barred.
07-02-2023 / Commodities & Trade
The Court of Appeal has considered, for the first time, the correct method of assessing damages in accordance with Default Clause 25(c) of GAFTA Contract No.24. In doing so, the Court of Appeal emphasised the compensatory principle underlying the award of damages under English law.
22-11-2022 / Commodities & Trade
Heytex Bramsche GmbH v. Unity Trade Capital Ltd [2022] EWHC 2488 (Ch) The Court has rejected a finance company’s contention that the documents presented under a letter of credit (LC) that it had issued were discrepant, rendering the LC void. Among other things, the issuer had sought to argue that the standard UCP 600 terms that were incorporated into the LC had been modified and overriden by additional terms, such that the documents were discrepant. The Court, however, emphasised that clear notice would have to be given to effectively incorporate such additional terms which were a clear departure from the UCP 600 and which conflicted with the commercial nature of a LC. Here, any notice given was insufficient and the issuer remained liable under the terms of the LC.
18-02-2022 / Commodities & Trade
Addax Energy S.A. v. Petro Trade Inc. [2022] EWHC 237 (Comm) In a dispute arising out of the supply of petroleum products, the English Court has dismissed a challenge to its jurisdiction, finding that the claimant supplier had a good arguable case that an English jurisdiction clause was incorporated into an alleged oral agreement by way of course of dealing. In doing so, the Court confirmed that the evidence required to establish a course of dealing need not be extensive or consistent to meet the relevant legal test.
18-02-2022 / Commodities & Trade, Maritime
In a recent ruling, the European Court of Justice (“ECJ”) was asked to consider the interpretation of Article 5 of EC Regulation No. 2771/96 of 22 November 1996 (commonly referred to as the “Blocking Regulation”) in relation to the termination, by a German telecoms company, of a contract with a bank subject to US sanctions.
12-01-2022 / Commodities & Trade
This commodities dispute highlights the importance of drafting a notice of arbitration carefully to ensure that it covers all the disputes that are intended to be referred to arbitration.