Menu
Contract in need of a CATS scan Interpretative treatment of lengthy long-term contracts

News / / Contract in need of a CATS scan Interpretative treatment of lengthy long-term contracts

BackgroundThe Central Area Transmission System (CATS) is a gas pipeline and transmission system which transports natural gas from several production fields in the North Sea to an onshore processing terminal in TeessideIn 1990, Teesside entered into an agreement with the CATS owners by which it reserved capacity in CATS over a 25 year period beginning in 1993 when CATS became operational Teesside was to pay a fee for the reserved capacity which was fixed for the first 20 years and calculated by reference to a contractual formula for the latter 5 years (Capacity Fee)In essence, the Capacity Fee was calculated by apportioning the operating and capital expenses payable by Teesside on the basis of the proportion of total pipeline capacity reserved to it under the contract and then applying a 15 upliftIssuesThe dispute concerned the calculation of the Capacity Fee, specifically the meaning and content of various elements of the contractual formula, includingThe scope of the defined term CATS Transportation Facilities (or CTF) as it related to various elements of operating and capital expenditure in the contractual formulaCategorisation of expenditure components of the formulaHow the total pipeline capacity was to be calculated for a given year andThe right of the CATS owners to restate the Capacity Fee and Teesside's good faith, or lack of it, in contesting the Capacity FeenbspResolving these issues required the court to consider the principles of contractual interpretation which apply to long, complex commercial contracts, and those unique to contracts which govern the parties' obligations over an extended periodPrinciples of interpretationBefore considering the individual issues of construction, the court set out several points that would guide its approach, in particularThe contract was a lengthy and complex document (which had been subject to multiple rounds of amendment) and even though expert advisers were engaged in the drafting process, it should not be assumed thatEvery phrase in such a document is as elegantly crafted or as logically integrated with every other as it might be desired orThe drafters will have envisaged every possible factual scenario which might arise under the contract over the course of the contract termnbspThe contract could be categorised as long-term, meaning it was appropriate for the court to adopt what it described as a flexible approach to the issues of interpretation to give effect to the reasonable expectations of the partiesThe court considered the flexible approach would extend to a certain (and fact-sensitive) degree of co-operation between the parties (per Globe Motors v TRW Lucas Varity Electric Steering 2016 EWCA Civ 396) but did not go so far as to give rise to a more generalised duty of good faith on both parties as suggested in Yam Seng Pte v International Trade Corp 2013 EWHC 111 (QB) in connection with similarly long-term relational contractsThe ordinary principles of construction require the court to engage in a unitary construction exercise by which it tests rival meanings of particular words and phrases against alternative meanings, the remainder of the contract, the contract's commercial purpose and the background to its formation (per Lord Hodge in Wood v Capita 2017 UKSC 24)DecisionThe individual points of interpretation are too numerous to recite individually, however the following two illustrate the court's approach to construction under the contractThe first issue the court considered was the scope of the CTF, namely whether it included four categories of equipment or components of the facilities Only expenditure incurred in connection with the CTF formed part of the Capacity FeeThe CTF was defined as the facilities to be constructed, owned and operated by the CATS owners, as described in Schedule I The CATS owners argued that the categories in dispute also formed part of the CTF as they were nevertheless ancillary to or associated with the transportation of gas within the pipelineThe court was not persuaded by this argument, largely on the basis that extending the definition in this way would mean that items of equipment such as pig receivers would also be considered part of the CTF This was held to be unlikely to have been the intention of the partiesThe final issue for the court concerned whether Teesside had an obligation to act in good faith in disputing the invoiced Capacity Fee The contract provided a right for either party to dispute, in good faith, any amount specified in an invoiceThe court found that the existence of this clause meant that it was not possible to imply a duty of good faith (per Legatt LJ in Globe Motors) as the contract exhaustively defined the extent of any good faith obligations In respect of the contractual obligation, it was found that by withholding certain sums after an audit had been completed and reviewed, Teesside's board were in breach of the express term by acting in bad faith in continuing to dispute the relevant parts of the Capacity Fee invoicesCommentAlthough the court adopted a clear and pragmatic approach parties should always take care when drafting long-term contracts, particularly where obligations arise late in the contract term, as it may be that the court will apply a more flexible approach than might be the case in other types of contract Similarly, if during the performance of a long-term contract the parties develop an understanding of how it is to be operated which is not reflected in the original wording, it would be prudent to record this in an addenda to the contractThe court's comments in relation to the duty of good faith in long-term relational contracts are also worthy of note the various references to good faith in the contract were sufficient to defeat an argument that a separate, generalised duty of good faith should be implied The English courts therefore continue to be reluctant to imply duties of good faith into contracts except in limited circumstances
Chris Kidd

Chris Kidd Head of Shipbuilding and Offshore Construction, Joint Head of Energy & Infrastructure, Partner

Related sectors:

Related services:

Related news & insights

News / Climate change litigation update: Derivative claim dismissed

06-07-2022 / Energy & Infrastructure

McGaughey & Anor v Universities Superannuation Scheme Ltd & Anor [2022] EWHC 1233 (Ch) On 24 May 2022, the High Court refused a claim brought against the directors of the Universities Superannuation Scheme (the “USS”), the largest private pension scheme in the UK, for inaction around climate change commitments.

Climate change litigation update: Derivative claim dismissed

News / Refund guarantees – avoiding drafting pitfalls

12-05-2022 / Energy & Infrastructure

Refund guarantees are often described as the cornerstones to shipbuilding projects and the buyer’s main security. Although they do not strictly form part of the shipbuilding contract, a shipbuilding project is unlikely to go ahead at all without one. It is therefore important to understand the different types of guarantee instruments, and the impact each has in practice on the guarantor’s obligations to pay and the buyer’s entitlement to recovery. A well-drafted guarantee provides certainty to the parties and strikes a balance between their respective entitlements and obligations.

Refund guarantees – avoiding drafting pitfalls

News / You will be estopped if you cross the line

04-04-2022 / Energy & Infrastructure

Estoppel is a useful tool in litigation, which is usually used to bind one party to a statement or a promise that it has previously expressed causing another to accept or adopt it for the purpose of their legal relations. The Court’s recent ruling in Geoquip Marine Operations AG v (1) Tower Resources Cameroon SA (2) Tower Resources PLC addresses estoppel by convention and recognises the requirement for the common assumption created between the parties to be clear and unequivocal. In this article, we focus on the specifics of the Court decision.

You will be estopped if you cross the line

News / Court of Appeal overturns second Unaoil bribery conviction

29-03-2022 / Energy & Infrastructure

On 24 March 2022, the Court of Appeal overturned the conviction of a second man, Paul Bond, prosecuted by the Serious Fraud Office (SFO) in relation to alleged wrongdoing by Unaoil. 

Court of Appeal overturns second Unaoil bribery conviction

News / The Court grapples with impact of Covid-19 on European rugby

08-03-2022 / Energy & Infrastructure

As we approach the second anniversary of Covid-19 being declared a pandemic by the World Health Organisation on 11 March 2020, a number of judgments are coming out of the English Courts which are providing useful guidance on how the English Courts are treating claims concerning Covid-19, especially in a force majeure context.

The Court grapples with impact of Covid-19 on European rugby

News / Climate change litigation: Courts decide the law, not political policies

02-03-2022 / Energy & Infrastructure

R (Finch) v Surrey County Council CA (Civ Div) [2022] EWCA Civ 187 “The task of the court in a claim such as this is only to decide the issues of law. Those issues cannot extend into the realm of political judgment – which is the responsibility of the executive, not the courts …”

Climate change litigation: Courts decide the law, not political policies