A stitch in SUPPLYTIME 2017

News /

In a decision handed down last month, the Commercial Court has considered, for the first time, the consequences under clause 12(e) of BIMCO SUPPLYTIME 2017 of failing to dispute an invoice before the due date: Boskalis Offshore Marine Contracting BV v Atlantic Marine and Aviation LLP (Atlantic Tonjer) [2019] EWHC 1213 (Comm).

Background

The case concerned the charter of a multi-purpose support vessel, the Atlantic Tonjer (the “Vessel”). On 9 April 2018, Atlantic Marine and Aviation LLP (the “Owners”) chartered the Vessel to Boskalis Offshore Marine Contracting BV (the “Charterers”) on an amended BIMCO SUPPLYTIME 2017 form.

Clause 12 (Hire and Payments) of the Charterparty had a number of additions, but the relevant sub-clauses (e)(Payments), (f)(Suspension and Termination) and (g)(Audit) were in unamended form. In particular, clause 12(e) provides:

"(e) Payments - Payments of hire, fuel invoices and disbursements for the Charterers' account shall be received within the number of days stated in Box 24 from the date of receipt of the invoice. Payment shall be received …  in full without discount or set-off …

If the Charterers reasonably believe an incorrect invoice has been issued, they shall notify the Owners promptly, but in no event no later than the due date, specifying the reason for disputing the invoice. The Charterers shall pay the undisputed portion of the invoice but shall be entitled to withhold payment of the disputed amount … "

It was agreed that payment was to be made within 21 days after issue of the invoices (Box 24).

Between 16 June 2018 and 13 July 2018, the Owners rendered invoices for hire, accommodation, meals and other services to the Charterers. The Charterers did not pay the invoices and the Owners commenced arbitration.

Tribunal decision

One of the issues that the Tribunal had to consider was the date by which the Charterers should have notified the Owners of an incorrect invoice and the consequences of failing to do so. 

The Tribunal determined that, if the Charterers wished to avoid their obligation to pay the invoices, they had to notify the Owners that an incorrect invoice had been issued within 21 days of receipt and that the consequence of failing to do so was that they came under an “obligation to pay [the Owners] the amount invoiced which they had not disputed within the relevant period”.

The Tribunal also concluded that clause 12(e) was not a time bar provision and that the Charterers’ characterisation of it as such was misconceived.

Commercial Court

The Charterers appealed to the Commercial Court on two questions of law:

  1. Whether clause 12(e) meant that the Charterers were debarred from raising defences against the invoices if they failed to notify the Owners before the due date for payment;  and
  2. Whether the Charterers were entitled to recover sums paid to the Owners which were not in fact due because the Charterers had a defence to the Owners’ claim for those sums (if that defence did not give the Charterers an independent counterclaim or a claim under the audit clause).

On question (1), the Charterers argued that the words of clause 12(e) were unclear and possibly ambiguous because they did not state that a failure to give notice would debar the Charterers from raising a defence to the sums claimed. The Charterers also argued that the clause was analogous to an exclusion or time bar and therefore needed to be clearer.

The Commercial Court agreed with the Tribunal and found that it was clear and unambiguous from the wording of clause 12(e) that the Charterers were barred from disputing the payment of invoices unless done so within the 21 days referred to in the contract. The Court highlighted the importance of cashflow for owners and the fact that the agreed periods in clause 12(e) were negotiated by two commercial parties of equal bargaining power. Accordingly, if the Charterers reasonably believed that there was an error in any invoice, they should have given the Owners the required notice under the clause within the time period specified because this is how the parties had bargained for disputes to be raised.

The Commercial Court also agreed with the Tribunal that the Charterers could always bring a counterclaim (including a claim for breach of contract or unjust enrichment) if they had paid sums which they later believed were not properly payable and, therefore, clause 12(e) was not analogous to a time bar or exclusion clause.

On question (2), the Commercial Court also upheld the Tribunal’s decision that the Charterers could not recover sums paid, even though they had a defence, if that defence was not a counterclaim in respect of financial loss resulting from such payment or by way of audit under clause 12(g). In other words, the Charterers could not raise off-hire defences which did not constitute a breach of contract unless they had notified the Owners of such defences before the due date of an invoice.

Therefore, the Charterers’ appeal was dismissed by the Commercial Court.

Comment

As this is the first opportunity that an English court has had to consider clause 12(e) of BIMCO SUPPLYTIME 2017, this case provides important clarification on the interpretation of this clause and the requirement for charterers to give prompt notice if they dispute an invoice (or part of it) and do not believe it should be paid.

In practice, charterers will lose their right to raise an off-hire defence if this is not notified promptly to owners, even in situations where charterers are not able to decide if they have such a defence within the agreed period for disputes to be raised (unless the claim can be construed as a claim for damages for the owners’ breach of the charterparty). Charterers should either seek to extend the period within which invoices may be disputed or ensure that any issues with the invoices are raised promptly and within the period agreed. It is also important for parties to be mindful that charterers may also have a remedy under the audit clause (although, depending on the wording, the audit clause may be much more limited in scope).

It is, however, worth nothing that, given that the wording of clause 12(e) was amended from SUPPLYTIME 2005, this does raise a question about whether the court would have reached the same decision in relation to clause 12(e) of SUPPLYTIME 2005.

Chris Kidd was a member of the SUPPLYTIME 2017 drafting committee.

Chris Kidd

Chris Kidd Head of Shipbuilding and Offshore Construction, Joint Head of Energy & Infrastructure, Partner

David Choy

David Choy Managing Associate

Related sectors:

Related news & insights

Insights / Climate Change Litigation Continueth – The Scottish Case: Greenpeace v. BEIS and the OGA (and BP too)

15-10-2021 / Energy & Infrastructure

The Scottish Court of Session has declared that dealing with the global environmental impact of the consumption of oil is a political matter for the UK Government, not a legal issue for the UK Courts in considering the validity of approval to drill new oil wells in a single field.

Climate Change Litigation Continueth – The Scottish Case: Greenpeace v. BEIS and the OGA (and BP too)

News / AfCFTA and Energy & Infrastructure

11-10-2021 / Energy & Infrastructure, Maritime

This article is the third in a series of articles looking at the impact of the African Continental Free Trade Area (the “AfCFTA”) on various practice areas and industry sectors that our clients operate in. This article focuses on Energy and Infrastructure and addresses some of the key questions our clients have asked us.

AfCFTA and Energy & Infrastructure

Insights / Supreme Court clarifies lawful act of duress

21-09-2021 / Energy & Infrastructure

In Times Travel (UK) Ltd v Pakistan International Airlines Corporation (Rev 2) [2019] EWCA Civ 828, the Supreme Court confirmed the existence of the doctrine of ‘lawful act duress’ under English law and its limited scope in commercial transactions.

Supreme Court clarifies lawful act of duress

News / Shell agrees pay out to Nigerian community to settle long-running oil spill dispute

17-08-2021 / Energy & Infrastructure

In 1991, the Ejama-Ebubu people began a legal campaign to hold Shell Nigeria (“Shell”) accountable for an oil spill that occurred in 1970. Shell accepted that these oil spills had occurred, but argued that these were caused by “third parties” during the Biafran war, for which Shell should not be held liable. Almost 20 years later, in 2010, a Nigerian Federal court ordered Shell to pay 17 billion naira to the Ejama-Ebubu community. Shell has unsuccessfully attempted to challenge this ruling over several years and, in November 2020, the Nigerian Supreme Court ruled that Shell could no longer appeal the decision.

Shell agrees pay out to Nigerian community to settle long-running oil spill dispute

News / The Bribery Act: ten years on

19-07-2021 / Energy & Infrastructure

The Bribery Act: ten years on

Quick links

The Legal 500 2021

“Very available and responsive to company developments in real time. Frank, clear advice – not just the ‘easy’ answer.”

The Legal 500 2022

“The solicitors who have handled our employment related issues are of the highest quality in terms of their specialist area of expertise, their professionalism and their approach to us as clients and as people. Special mention has to be made of Laura Livingstone. Laura became a key member of our team and felt more like a colleague than an external adviser – a colleague you could rely upon. Laura’s attention to detail, professionalism and responsiveness was second to none. Laura has come to know and understand us as individuals and this has enabled her to personalise her advice and even sometimes to preempt our future requirements. We have a very special and extremely valuable relationship with her and the firm.”

- The Legal 500

The Legal 500 2022

“Ince are an excellent “fit” with our specific needs. The firm has consistently provided a broad range of personnel-related advice and in our experience that advice has been consistently of the very highest professional standard: it has been timely, comprehensive, accurate and at a cost which is commensurate with the budget of an organisation of our size.”

- The Legal 500

The Legal 500 2022

“The firm has an unusually high degree of insight into the practices and policies required by the Gambling Commission as regards compliance with its own requirements and conditions – particularly Andrew Tait, derived from his previous in-house experience.”

- The Legal 500