Menu
LMAA brings clarity to arbitration notifications

News / / LMAA brings clarity to arbitration notifications

In November 2018, the London Maritime Arbitrators Association (LMAA) released a new Arbitration Notice Clause. This new clause, which parties can incorporate into their dispute resolution provisions, provides for the designation of individuals and e-mail addresses for the service of arbitration notices and communications, ensuring that each party identifies those authorised to accept service of legal proceedings on its behalf.

Unlike court proceedings, which have their own specific Civil Procedure Rules that dictate the necessary formalities for starting a claim, arbitrations are usually commenced by serving the relevant notice on the opposition. An ineffective notice of arbitration may render the arbitration proceedings invalid, though any challenge to this may not arise until after a final award has been given by the tribunal. It is, therefore, paramount that any notice is served correctly in order to protect the claimant’s position.

Failure to commence arbitration effectively also means that time does not stop running for the purpose of limitation and contractual time bars. As such, a claimant who fails to properly commence arbitration due to a procedural error in the arbitration notice runs the risk of losing its right to bring the claim altogether, notwithstanding that it has incurred significant legal costs in the pursuit of its claim and may believe it already has an enforceable arbitration award in its favour.

Case law

One case where this happened was Glencore Agriculture B.V. v Conqueror Holdings Limited [2017] EWHC 2893 (Comm). In this case Glencore sought to set aside an arbitration award made against it on the basis that it was unaware of the proceedings until it received the final award by post, some 14 months after Conqueror had sent its initial letter before action.

In order to commence proceedings, Conqueror sent a notice of arbitration to the work email address of a junior employee of Glencore, whose role was purely operational. The notice was neither acknowledged nor replied to, and several further emails from both Conqueror and the arbitrator were also sent to this individual’s email address and went unanswered. Subsequently, the arbitrator made an award in Conqueror’s favour.

Glencore sought relief under section 72 of the Arbitration Act 1996, on the basis that the award had been made without jurisdiction and/or the tribunal had not been properly constituted and/or that no matters of dispute between the parties had been submitted to the arbitration in accordance with the arbitration agreement. Glencore succeeded in setting aside the award on the basis that service of the arbitration notice was not effective.

To resolve the dispute, the court turned to agency principles and concluded, examining the facts objectively, that the employee did not have express, implied or ostensible authority to accept service; given his position, the individual who received the relevant correspondence was not someone who was authorised to accept legal process on behalf of the company.

Another case which looked at the issue of whether arbitration had been commenced effectively, albeit with a different outcome, was Sino Channel Asia Ltd v Dana Shipping and Trading Pte Singapore and Another [2017] EWCA Civ 1703. On the facts of this case, following an appeal, the Court of Appeal held that service had been effective as the recipient of the notice had actual implied authority and/or ostensible authority to accept the notice. However, it also commented that, on the facts, a recurrence of the situation was likely to be rare.

Comment

It is worth noting that section 76(4) of the Arbitration Act permits service of any notice related to an arbitration by post to a company’s registered or principal office. If this is done then any such notices will be treated as effectively served; a point that was made in both cases above as neither claimant in the arbitration chose to serve its notice of arbitration by this method despite the protection it would have afforded them.

These cases demonstrate the potential pitfalls involved with a failure to commence arbitration effectively, and the time and costs that can subsequently be lost in having a further dispute over whether an arbitration award is enforceable. The new LMAA Arbitration Notice Clause, if used and administered correctly, should provide clarity to contractual parties on the steps they need to take to commence arbitration when a dispute seems likely to materialise.

Related sectors:

Related news & insights

News / UAE Ministerial Directive Gives the Green Light towards Allowing Enforcement of English Court Judgments onshore the UAE

21-09-2022 / Energy & Infrastructure

On 13 September 2022, the UAE Ministry of Justice (MOJ) issued a landmark directive to the President of the Dubai Courts, referring to a recent English Court judgment in Lenkor Energy Trading DMCC v Puri (2020) EWHC 75 (QB) which enforced a UAE Court judgment, and urging the Dubai Courts to take requisite steps to follow the principle of reciprocity when it comes to enforcing English Court judgments in the UAE.

UAE Ministerial Directive Gives the Green Light towards Allowing Enforcement of English Court Judgments onshore the UAE

News / Climate change litigation update: Derivative claim dismissed

06-07-2022 / Energy & Infrastructure

McGaughey & Anor v Universities Superannuation Scheme Ltd & Anor [2022] EWHC 1233 (Ch) On 24 May 2022, the High Court refused a claim brought against the directors of the Universities Superannuation Scheme (the “USS”), the largest private pension scheme in the UK, for inaction around climate change commitments.

Climate change litigation update: Derivative claim dismissed

News / Refund guarantees – avoiding drafting pitfalls

12-05-2022 / Energy & Infrastructure

Refund guarantees are often described as the cornerstones to shipbuilding projects and the buyer’s main security. Although they do not strictly form part of the shipbuilding contract, a shipbuilding project is unlikely to go ahead at all without one. It is therefore important to understand the different types of guarantee instruments, and the impact each has in practice on the guarantor’s obligations to pay and the buyer’s entitlement to recovery. A well-drafted guarantee provides certainty to the parties and strikes a balance between their respective entitlements and obligations.

Refund guarantees – avoiding drafting pitfalls

News / You will be estopped if you cross the line

04-04-2022 / Energy & Infrastructure

Estoppel is a useful tool in litigation, which is usually used to bind one party to a statement or a promise that it has previously expressed causing another to accept or adopt it for the purpose of their legal relations. The Court’s recent ruling in Geoquip Marine Operations AG v (1) Tower Resources Cameroon SA (2) Tower Resources PLC addresses estoppel by convention and recognises the requirement for the common assumption created between the parties to be clear and unequivocal. In this article, we focus on the specifics of the Court decision.

You will be estopped if you cross the line

News / Court of Appeal overturns second Unaoil bribery conviction

29-03-2022 / Energy & Infrastructure

On 24 March 2022, the Court of Appeal overturned the conviction of a second man, Paul Bond, prosecuted by the Serious Fraud Office (SFO) in relation to alleged wrongdoing by Unaoil. 

Court of Appeal overturns second Unaoil bribery conviction

News / The Court grapples with impact of Covid-19 on European rugby

08-03-2022 / Energy & Infrastructure

As we approach the second anniversary of Covid-19 being declared a pandemic by the World Health Organisation on 11 March 2020, a number of judgments are coming out of the English Courts which are providing useful guidance on how the English Courts are treating claims concerning Covid-19, especially in a force majeure context.

The Court grapples with impact of Covid-19 on European rugby